BG Releases 16-Week Office Fit-Out Timeline Guide

2026-11-08

BG Office Furniture has published a 16-week office fit-out timeline that maps when furniture must be ordered against partition, flooring, ceiling and electrical works. The guide answers the question that comes up at the start of almost every project: how much time should really sit between the furniture PO and the handover date.

Three procurement routes, three PO cut-offs

The guide splits procurement into three routes with different lead times. Custom import takes 70–100 days door to door — 25–35 working days of production, 14–21 days at sea, 3–7 days of customs, plus buffer — so the PO should be released no later than 16 weeks before handover. Ready-stock import sits at 35–50 days, and local distributor stock at 3–14 days.

Sequence drives cost

Furniture is the last trade on site but the earliest decision, the guide notes. Three hidden costs appear when the sequence is wrong: temporary storage, rework of power points, and a slipping schedule. Working drawings and technical specifications therefore need to be signed before the deposit is sent, not after the 3D render is approved.

Realistic buffers

The guide recommends a 5–10% quantity buffer, a two-week schedule buffer and a 3–5% budget buffer on the furniture value. On an import project, a single container held two weeks over missing documents can wipe out the contractor’s entire margin.

BG catalogue context

The guide is drawn from project practice using the BG catalogue: 787 models across 8 categories — executive desks, manager desks, staff desks, workstations, meeting tables, filing cabinets, coffee tables and reception desks. MOQ is 20 pcs per model, production runs 25–35 working days, structural warranty is 5 years, and shipments use Form E (ACFTA).

Schedule highlight: W5 is the pivot

In the 16-week map, the furniture PO is issued in week five — alongside the main contractor tender, not after the partitions are finished. On import projects, a two-to-three-week difference at this point is usually enough to save the handover date. The map also marks W12–W14 as the customs and site-delivery window, and W14–W15 for knock-down installation.

The three documents that decide claims

The guide closes with three handover documents: a packing list per carton that matches the physical count, installation minutes with photos per area and defect notes, and handover minutes signed by both parties with a clear claim deadline. Without them, a production defect is hard to separate from installation damage.

For 2027 projects

Projects targeting a first-quarter 2027 handover need working drawings and the PO closed before the end of 2026, because production and shipping run through the peak demand period ahead of Chinese New Year. For second-quarter projects, the PO window remains open in January–February.

How to use the guide

The full guide is available at Office Fit-Out Timeline: When to Order Furniture. Project teams can send the layout, unit counts per area and handover date to receive a tailored PO schedule through the contact form or sales001@fsbige.com.