Office Fit-Out Timeline: When to Order Furniture

2026-11-08

Office fit-outs rarely fail because the furniture is poor. They fail because the sequence is wrong: desks arrive before the flooring is finished, partitions go up after the cables are pulled, or the import PO is only raised once the ceiling is closed. The result is furniture stacked in the work area, scratched panels, and a handover date that slips by one or two weeks.

This article sets out a 16-week office fit-out sequence: when working drawings must be signed off, when the furniture PO has to be issued, how furniture interlocks with partitions, flooring, ceiling and electrical works, and which buffers are realistic. Product examples reference BG workstations, staff desks, meeting tables and filing cabinets.

Why sequence drives cost

Furniture is the last trade to enter the site, but the earliest decision to make. Three hidden costs appear when the sequence is wrong. First, storage cost: goods that arrive too early sit in a temporary warehouse billed by the cubic metre per day. Second, rework cost: power points that do not match the desk drawing force panels to be opened or surface trunking to be added. Third, schedule cost: a one-week delay on a leased floor means rent, electricity and salaries keep running with no productivity.

The right sequence therefore always runs from documents to production to installation — never the other way round. Working drawings and technical specifications must be complete before the PO, because changes after production starts almost always mean extra cost and a re-planned schedule.

The 16-week office fit-out map

The table below is the sequence commonly used for a 500–2,000 m² office with imported furniture. Smaller projects or those using local stock can compress several rows.

WeekBuilding & MEP worksFurniture worksKey documents
W1–W2Site survey, measurement, strip-out of old partitionsDemand calculation per area: desks, storage, meeting roomsSpace programme, layout plan
W3–W4MEP working drawings, power points, HVACModel, colour and configuration selectionTechnical spec, furniture working drawings
W5Main contractor tender or appointmentRFQ to factory, quotation comparison, negotiationPO, 30% deposit, production schedule
W6–W9Partitions, ceiling, electrical, flooringProduction 25–35 working days, pre-shipment QCQC report, production photos
W9–W12Floor finishing, painting, light fittingsShipment, export documents, arrivalPacking list, Bill of Lading, Form E
W12–W14Final cleaning, MEP testingCustoms clearance, delivery to siteImport declaration, delivery note
W14–W15Building snaggingKnock-down installation, assembly, placementInstallation minutes
W16Building handoverFinal inspection, claims, maintenance briefingHandover minutes

Note that the furniture PO is issued in W5, alongside the building tender — not after the partitions are finished. On import projects, a two-to-three-week difference at this point is usually enough to save the handover date.

Three procurement routes and their lead times

Lead time is not one number. It depends on the route, and each route has a different PO cut-off.

RouteBest forTypical door-to-door lead timeLatest PO
Custom import (built to specification)100+ units, special colours and sizes70–100 days: production 25–35 working days + sea freight 14–21 days + customs 3–7 days + buffer16 weeks before handover
Ready-stock import30–100 units, standard catalogue models35–50 days8–10 weeks before handover
Local distributor stockUrgent needs, extra units, small meeting rooms3–14 days3–4 weeks before handover

For projects that mix routes, the practical rule is: custom goods first, ready stock next, and locally bought extras close to the handover date. The production-to-container detail is covered in the production lead time article.

The critical points: when the PO must be released

Before flooring is finished

Vinyl, carpet tile and epoxy are usually the last trades before furniture. If the furniture PO has not been released when flooring starts, the goods will most likely arrive after the floor is complete — and installation becomes an open-ended wait. Fix the flooring date, then work backwards to the PO date.

Before the ceiling is closed

Power points, cable routes and floor boxes must be set from the desk working drawings, not from estimates. A desk with an under-surface cable tray needs different outlet positions from one without. Once the ceiling is closed and the floor laid, adding power points means opening finished surfaces.

After working drawings are approved — not after the 3D render

3D renders are for presentation; production runs from working drawings: per-model dimensions, cable-hole positions, edge-banding type and per-panel colour. Make sure the working drawings are signed before the deposit is sent. Colour or size changes after production starts are generally treated as a new order.

Interlocking with other trades

Partitions, flooring, ceiling and electrical works do not run in isolation. Acoustic partitions determine desk positions; desk depth determines screen viewing distance; ceiling height determines the pendant choice above a meeting table. In open-plan areas, the partition and acoustic screen decision should be taken together with the workstation layout, because both share the same module.

The item most often missed is the cable route between desk rows. Bench workstations usually pull cable along one main spine, then branch to each desk. If the spine is not fixed before flooring goes down, cables end up on the surface and create extra finishing work at the end of the project.

Buffers you should carry

Three buffers keep the schedule realistic without adding major cost. Quantity buffer: 5–10% extra units for spaces that change during installation, especially desks and storage. Schedule buffer: two weeks before the handover date, for customs, short shipments or on-site repairs. Budget buffer: 3–5% of the furniture value for extra freight, re-installation and replacement panels.

These buffers are not waste. On an import project, a single container held for two weeks over missing documents can wipe out the contractor’s entire margin.

Handover: the three documents that decide claims

On the final day, what matters is not how many items arrived but how complete the paperwork is. First, a packing list per carton that matches the physical count. Second, installation minutes listing installed units, photos per area and defect notes. Third, handover minutes signed by both parties with a clear claim deadline.

Without those three documents, a production defect is hard to separate from installation damage. The detailed guide is in the office furniture handover checklist, while the assembly order is in the knock-down installation guide.

Office fit-out timeline FAQ

How long does a 1,000 m² office fit-out take?
Typically 14–18 weeks from working drawings to handover, with custom import furniture as the longest route. Offices under 300 m² using local stock can finish in 6–10 weeks.

Can furniture be ordered before the main contractor is appointed?
Yes, provided the working drawings and specification are final. The risk is ordering before the layout and power points are agreed, because post-production changes add cost.

When is the safest time to order for a January handover?
For custom imports, the PO should be placed by late September to early October. From November onwards, the realistic options are ready stock or a mix with local stock.

What if the handover date moves forward by two weeks?
There are two levers: expedite production at extra cost, or split the shipment — some units first by air or from local stock. Both need to be decided at least four weeks before the new date.

Need help building the schedule, working drawings or a project quotation? Send your requirement list through the contact form or email sales001@fsbige.com, Tel/WeChat +86-18928562556. The full catalogue is on the products page.