Office furniture transit time from China to Indonesia is not a single number. When an importer asks “how long until my goods arrive”, two phases must be separated: factory production (25–35 working days for regular orders) and ocean freight (7–18 days depending on the destination port). Adding the two carelessly is the most common reason project installation dates slip.
This guide provides a port-by-port sea transit table — Tanjung Priok, Tanjung Perak, Tanjung Emas, Belawan, Makassar, Balikpapan and Batam — plus a full timeline from PO to warehouse. The figures are the working ranges the BG Office Furniture team uses when planning shipments for distributors and project contractors in Indonesia.
Phase 1: production of 25–35 working days
A factory does not ship office furniture off a shelf. Every order is produced after the PO and deposit are received: panel cutting, edge banding, frame assembly, finishing, then quality control. For standard orders, BG's production schedule is 25–35 working days. Custom orders — special colours, non-catalogue sizes or module combinations — usually add 5–10 working days for drawing approval and colour samples.
If a project has a fixed handover date, count backwards from it: subtract 45–65 days, not 15. The stage-by-stage breakdown is in our production lead time guide.
Phase 2: ocean transit of 7–18 days
Once production is finished, the goods still go through vessel booking, container stuffing and PEB export declaration. That stage takes 3–7 days. Ocean transit starts only when the vessel sails.
| Destination port | Sea transit | Typical routing | Clearance + trucking |
|---|---|---|---|
| Tanjung Priok (Jakarta) | 7–10 days | Direct from Shekou, Yantian or Nansha | 3–7 + 1–2 days |
| Tanjung Perak (Surabaya) | 7–10 days | Direct, or via Jakarta (+3–5 days) | 3–7 + 1–3 days |
| Tanjung Emas (Semarang) | 9–13 days | Usually via Jakarta or Singapore | 3–7 + 1–3 days |
| Belawan (Medan) | 9–14 days | Direct or transhipment via Singapore | 3–7 + 1 day |
| Makassar (Soekarno-Hatta) | 12–18 days | Via Surabaya or Jakarta | 4–8 + 1–3 days |
| Balikpapan / Samarinda | 12–18 days | Via Surabaya, then feeder | 4–8 + 2–5 days |
| Batu Ampar (Batam) | 6–9 days | Via Singapore | 3–7 + 1 day |
Two notes matter. First, direct calls from South China are far more stable than transhipment routings; the difference can be 3–7 days. Second, sailings to ports outside Java often run only once a week, so missing a cutoff by one day can mean a seven-day wait.
Full timeline: from PO to warehouse
| Stage | Duration | Note |
|---|---|---|
| PO confirmation + deposit | 1–3 days | Specs, colours and warehouse address locked |
| Production + QC | 25–35 working days | Custom adds 5–10 working days |
| Vessel booking + stuffing + PEB | 3–7 days | Slot booked before production ends |
| Ocean transit | 7–18 days | Port dependent; transhipment +3–7 days |
| PIB clearance + VAT/income tax | 3–7 days | Documents must match the Form E |
| Trucking + unloading | 1–5 days | Depends on port-to-warehouse distance |
| Total, PO to warehouse | 45–65 days | Greater Jakarta 45–55; outer islands 50–65 |
Five things that usually add one to two weeks
- Inconsistent documents. Form E, invoice and packing list must state the same product, quantity and weight. One mismatched line can hold clearance for days.
- Unplanned transhipment. A vessel calling at Singapore or Port Klang adds 3–7 days; confirm the final routing before promising a date to your client.
- Weather and peak season. November–February brings high seas; around Chinese New Year and Lebaran, vessel slots fill and container trucks become scarce.
- Wrong CBM calculation. A 5% error on a 60 m³ load can force an extra container or a split shipment. Use our container loading table as a baseline.
- Slow custom approval. A colour sample delayed by two weeks shifts the entire production schedule.
Four ways to cut time without adding cost
- Book the vessel slot when production reaches 70%, not when it finishes. This saves 3–5 days at no extra cost.
- Send the draft Form E with the invoice so it can be validated before stuffing. See our Form E ACFTA guide.
- Combine several rooms in one mixed container so no follow-up shipment waits for the next sailing.
- Choose the port closest to the project: Tanjung Emas for Central Java, Tanjung Perak for East Java, Belawan for North Sumatra. Shorter trucking saves 1–3 days and cost.
Verifiable company facts
- Legal name: Foshan BG Office Furniture Co., Ltd. (佛山市毕戈家具有限公司)
- Unified social credit code (USCC): 91440606MA4UKCYD6A
- Established: 2015 — 10,000 m² factory in Foshan, Guangdong
- Certification: Bureau Veritas audit (MIC-ASR2611191); E1/E0 boards available on request
- Exports: 50+ countries; mixed containers and Form E ACFTA for Indonesia
- Lead time: 25–35 working days for production orders; FOB Shenzhen/Guangzhou or CIF Jakarta–Surabaya
FAQ: office furniture import transit time
How long from PO to goods in Jakarta? About 45–55 days: 25–35 working days of production, 7–10 days of sailing to Tanjung Priok, then 4–9 days for clearance and trucking.
Can shipping be faster? One to two weeks faster is possible by booking the vessel before production ends, having documents ready from day one and choosing non-custom models. Under 30 days is not realistic for fresh production.
Which port is fastest for Java? Tanjung Priok for Greater Jakarta, Tanjung Perak for East Java, Tanjung Emas for Central Java. All have direct services from South China with 7–13 days of transit.
Need a shipping schedule for your project? Send your requirement list — product type, size, quantity and destination city — through the contact form or email sales001@fsbige.com. The team replies with specifications, FOB pricing and a transit estimate to your port. Tel/WeChat: +86-18928562556. The full catalogue is on the products page.