Chinese New Year 2027 Cut-Off: When to Order Office Furniture

2026-11-03

Chinese New Year 2027 falls on 6 February 2027 — 95 days from early November 2026. Foshan furniture factories typically stop production around 29 January and return to normal after 22 February, leaving roughly three weeks without output in the middle of the Q1 shipping season. For an order that must arrive at a Jakarta warehouse on 15 January 2027, the PO and deposit have to be in by 21 November 2026: 35 days of production, 3 days of stuffing, 7–10 days at sea and 3–7 days of clearance. If the goods must be in hand before Chinese New Year (5 February 2027), the PO deadline is 11 December 2026; for early-February arrival, 17 December 2026 with the container sailing before 19 January 2027.

This guide contains the six-stage production calendar, a countdown table from arrival date back to PO date, the buying patterns most common among Indonesian importers, and a checklist for locking a production slot before the factory closes. Figures come from the team at Foshan BG Office Furniture Co., Ltd. (USCC 91440606MA4UKCYD6A, founded 2015, Bureau Veritas-audited 10,000 m² factory, exports to 50+ countries, 300+ containers per year).

Why the Chinese New Year calendar sets your schedule

Chinese New Year is not a single holiday. Companies in Guangdong usually give 10–20 days off, and the effect is felt two weeks before and two weeks after:

  • Labour — most operators come from outside Guangdong and travel home; the departure wave starts 10–14 days before the holiday.
  • Trucks and stuffing — truck capacity to Nansha/Shekou drops, rates rise, and stuffing slots must be booked earlier.
  • Vessel booking — every shipper chases the last sailing before the break, so documentation cut-offs tighten and space fills fast.
  • Post-holiday ramp-up — the first week after reopening is usually spent calibrating lines and retraining, not running at full output.

In practice, one week of delay before Chinese New Year can mean goods arriving two to three weeks later, because production has to wait for the factory to reopen.

Production calendar: six stages and their durations

The table below is the sequence we use for export orders, counted from PO receipt to vessel departure.

StageNormal durationWhat gets locked here
1. PO & specification confirmation2–5 daysModel, size, colour, accessories, container mix
2. 30% deposit1–3 daysProduction slot enters the schedule
3. Material procurement3–7 daysMelamine panels, hardware, powder coating
4. Production & finishing18–25 daysLine schedule, labour, QC dates
5. QC & export packing3–5 daysStage-by-stage QC photos, cartons, foam, pallets
6. Stuffing & documents2–3 daysForm E, packing list, vessel booking, BL

Total 25–35 days after deposit for standard orders. Colour or size customisation adds 7–10 days; exclusive design with samples adds 2–3 weeks.

Countdown: when the PO has to be in

The figures below assume the worst case — 35 days of production, 3 days of stuffing, 7–10 days at sea to Jakarta and 3–7 days of clearance — so the plan survives peak season.

Target arrival at warehousePO + deposit byContainer must sail byNote
20 December 202626 October 20263 December 2026Already passed; stock models only
15 January 202721 November 202629 December 2026Safest window — 18 days from now
5 February 2027 (before Chinese New Year)11 December 202619 January 2027Safe limit when goods must be in hand before the shutdown
10 February 202717 December 202624 January 2027Production must finish before the shutdown
5 March 20279 January 2027 or after 15 February 202716 February 2027Production is split by Chinese New Year — pick one window

For other ports, add the transit difference: Surabaya +3–4 days, Semarang +3–5 days, Medan +5–8 days, Makassar +5–8 days, Balikpapan +7–10 days. Routes and transit times are detailed in our China–Indonesia shipping guide.

For budgeting: one 40HQ container of mixed staff desks, workstations and cabinets is worth USD 11,400–30,500 FOB, or roughly USD 14,400–35,700 landed in Jakarta. That is the figure procurement teams usually take to management.

Three buying patterns and the schedule we recommend

1. Q1 office fit-out projects. Office opening January–March. PO in November, arrival December–January, installation two weeks before handover. This is the pattern we handle most often for branch offices and regional government offices.

2. Distributor restocking. Warehouse stock must be full before procurement season. PO in November for January arrival, then a second PO in early February that is produced after the factory reopens (arriving in April). This avoids a February–March stock gap.

3. Urgent purchases. Extra units for a tender won at short notice. The answer is stock models in standard colours — about 15–20 days faster — or LCL when volume is under 15 CBM. For small volumes LCL still makes sense even though the cost per CBM is higher.

What most often breaks the schedule

  • Non-standard colours or finishes locked only after production starts — adds 7–10 days.
  • Design changes after the PO — redraw, resample, and the production slot shifts 1–2 weeks.
  • Samples not yet approved while mass production is already scheduled.
  • Late documents — Form E and packing list must be ready 5 days before ETD; without Form E the 0% ACFTA rate does not apply and duty returns to normal.
  • Last-minute vessel booking — in the final week before Chinese New Year space is the most expensive and fills fastest.
  • Wrong CBM calculation — the container under-loads or leaves dead space; see our 20ft & 40HQ load guide.

Checklist for locking a production slot before Chinese New Year

  1. A written PO with a target arrival date, not just “ASAP”.
  2. The 30% deposit paid — a production slot only enters the schedule once the deposit is received.
  3. Colour and finish codes locked before production (for example G17, G21, G28, B4).
  4. A written production schedule and QC photo dates per stage.
  5. ETD and documentation cut-off confirmed with your forwarder at least three weeks before sailing.
  6. Invoice, packing list, Form E and BL instructions ready five days before ETD.
  7. A seven-day buffer in the office opening or customer delivery plan.

If you are combining several series in one container — executive desks, workstations, file cabinets, meeting tables — sequence production so that every model finishes in the same week. How to structure it is covered in our mixed container guide, and examples of the models ordered most often are the BG-24817W12 workstation and the 1121A executive desk.

FAQ

What is the deadline to arrive before Chinese New Year 2027?
For Jakarta, PO and deposit by 21 November 2026 to arrive on 15 January 2027. For early-February arrival, the PO deadline is 17 December 2026 and the container must sail before 19 January 2027.

Do factories really close for Chinese New Year?
Yes. Production usually stops for 10–20 days; trucking and labour are already constrained a week before the break, and the first week after reopening is ramp-up.

Can production be accelerated?
For stock models in standard colours, 25 days is achievable. For full customisation, speeding up means cutting QC time — and the risk of transport damage rises.

Is a mixed container still possible before Chinese New Year?
Yes, as long as every model is locked in the same PO. A 40HQ holds 66–76 CBM; a mix of desks, workstations and cabinets usually reaches that with 60–90 units.

Next step

Send your model list, quantities and target arrival date through the contact page or email sales001@fsbige.com / Tel/WeChat +86-18928562556. We reply with a written production schedule and an FOB/CIF quotation within 2 working hours. Full catalogue: https://bgofficef.com/produk/.